Bridge production: shipping parts while your injection mould is being made
You have orders, the mould is ordered and the toolmaker needs weeks or months. Bridge production fills that gap with a process that needs little or no tooling. The risk is not the bridge itself but the switch: customers get parts from two processes, so dimensions, colour and fit have to match well enough. Plan the bridge as a small production run with its own acceptance criteria, not as a favour from a print shop.
Pick the bridge process by part size and quantity
Small to medium parts in the low thousands: MJF or SLS printing farms, which run many machines in parallel. Large parts (ASA or PETG enclosures, panels): large-format FDM farms, which are slower per part and need more finishing. Parts that must look and feel moulded, in the low hundreds: vacuum casting. Higher quantity of a simple part: a soft tool, meaning an aluminium or printed mould insert that runs a few hundred to a few thousand shots in a standard moulding machine.
Write down what "same part" means
List the dimensions that matter for fit and function, the cosmetic faces, colour and texture, and the mechanical properties the part must reach. Printed nylon, printed ASA and moulded ABS behave differently in heat, UV and impact, so check the bridge material against the real use, not only against the drawing. Agree this list with the bridge supplier before the first batch.
Order a first article before the run
Ask each candidate shop for one or two first-article parts from your production file, then measure them against your list: warpage on large flat faces, hole positions, snap-fit strength, colour next to a moulded sample if you have one. Large FDM parts in particular can warp, and that only shows on the real geometry.
Capacity is the real question
A bridge run fails when a shop cannot hold the weekly rate. Ask how many machines the job would use, the weekly output they commit to, what happens when a machine is down, and whether they will split the order across sites. For a large run, two suppliers in parallel are often safer than one.
Design the part for both processes
Keep features that both processes can make: draft on vertical faces (harmless for printing, required for moulding), uniform walls, no undercuts that only the mould can produce. If the moulded part will have textured surfaces, decide whether the bridge parts get a matching finish or are sold as a first edition.
What to send for a bridge quote
The production STEP file, the critical dimension list with tolerances, material and colour, target finish, the weekly quantity and the total, the date the mould is expected, quantity breaks and ship-to country. Asking for the bridge quote and the tool quote at the same time also shows you the break-even point between the two.
Planning the parts around it
If the moulded part is one of several in your product, list them all: which are bought, which are made and by whom. Our prototype planner does that split from a product description and lists manufacturers per process; the figures there are rough estimates, not quotes.